92 feet onthe Rubicon.
Job 25-041, Cape Coral. A 1968 seawall replaced in precast concrete, with a new dock and a four-pile lift.
- 92LF
- Seawall
- 19
- Panels
- 420SF
- Dock
- 16,000LB
- Lift
- 12WK
- Start to final
- 2025
- Finished in June
Forty feet
of split cap.
Carol and Jim's wall had held since 1968. By 2024 the cap had opened along forty feet and the lawn behind it dropped a little after every hard rain. Two contractors quoted the job. Neither would put a date on it.
Week 1–3
Probe, survey, seal
We probed the 1968 panels, sounded the canal off the wall and had the drawings back from the engineer, sealed, in week three.

Week 4–10
Paper out, panels curing
The state verification came back in 26 days and the city permit three weeks after it. Nineteen panels were cast the day the paper went in and cured the whole time it was out.

Week 11
The Irene ties up
Old cap cut and hauled, nineteen panels jetted in, ten tie rods run back to new anchors. The city passed the panels on Thursday.

Week 12
Cap, dock, lift
The cap went in as one pour, 24 inches above the old one. Then eight dock piles, 420 square feet of deck and a 16,000 lb lift on four ten-inch piles. Final inspection passed on the Friday.


They told us thirteen weeks in March and handed us the final inspection in week twelve.
Carol and Jim P. Google review, June 2025
- Their boat
- 31 FT
- Loaded
- 12,225 LB
- With 20%
- 14,670 LB
- Lift
- 16,000 LB